This is the project introduction for the ALASKA FIRE PROTECTION SYSTEM – DC FG WAREHOUSE project, based on the Weekly Progress Report No. 10 covering April 01–07, 2026
The project, which runs from February 2026 to April 2027, has reached an overall progress of 25.99% as of April 07, 2026.
Key Accomplishments (Completed Work):
- Installation of 58 pieces of pipe support at the perimeter wall.
- Approval and signing of Method Statements (MS) for Pump House to DC Warehouse pipe layout and unloading of pipes using a forklift.
- Approval and signing of Hazard Identification and Risk Assessment and Control (HIRAC) for Pump House to DC Warehouse pipe layout and unloading of pipes using a forklift.
Current Ongoing Activities:
- Fabrication of pipe support.
- Continuous installation of pipe support at the perimeter wall outside the DC Warehouse.
- Installation of brackets and supports (angle bar brackets, U-bolts, expansion shields)
- Continuous installation of supports around the warehouse perimeter